General Scope of Work: All labor, equipment, materials, and contracts required to perform bridge load ratings of the identified railroad bridges. Covered work includes mobilization/demobilization, bridge load ratings for identified bridges of The Owego & Harford Railway, Inc. (OHRY), bridge load ratings for identified bridges of Lehigh Railway, LLC (LRWY), and associated data packages.

December 2, 2016 - Bid package released.  Invitation to bid sent to 5 firms.

January 3, 2017 - Addendum 001 released. Removed liquidated damages clause from bid form.

January 10, 2017 - Field survey of bridges.

January 11, 2017 - Addendum 002 released.  Changed allowable forms of submission to include email or fax.  Updated OHRY bridge inventory list.

January 13, 2017 - Bid openning.  Erman Anthony was lowest qualified bid.

                              Erdman Anthony $39,442.00
  Stone Consulting and Design     $41,340.00
  Keller Engineers $48,500.00
  CSR Engineering $48,900.00
  HDR $79,694.20

 

 

 

 

 January 17, 2017 - Executed Notice of Award and Contract.

May 16 & 17, 2017 - Took measurements of LRWY bridges.

June 12-14, 2017 - Took measurements of OHRY bridges.

General Scope of Work: Construction of a railroad siding, replacing timber structures with culvert piping, replacing bridge timbers and repair of timber bridges.

March 7, 2013 - Bidding documents released. Invitiation to bid advertisement placed in 3 newspapers and OHRY website. Additionally, facsimile copies of bid advertisement sent to 13 maintenance of way contractors.

March 19, 2013 - Mandatory pre-bid meeting held at 25 Delphine St, Owego, NY. 22  potential bidders attended.

March 20, 2013 - Addendum 001 released. Incorporated answers to clarification questions from pre-bid meeting into contract package and changed the due date to April 17, 2013.

April 17, 2013 - Sealed bid proposals due by 4:00 pm.  5 bids received.

April 29, 2013 - Recommended contractor submitted to New York Department of Transportation (NY DOT) for approval.

May 7, 2013 - NY DOT concurs with the selection of Atlas Railroad Construction with a bid of $916,900.00.

May 10, 2013 - Executed contract between Atlas Railroad Construction and The Owego and Harford Railway, Inc. in the amount of $916,900.00. Line item pricing shown below.

No.Item

Quantity

Unit Price

Extended Price
OH1 Mobilization 1 LS $26,550.00 $26,550.00
OH2 Furnish and Install Track 4,400 TF $94.00 $413,600.00
OH3 Furnish and Install #8 Turnouts 2 ea $58,000.00 $116,000.00
OH4 Furnish and Install Stone Ballast 2,000 T $34.00 $68,000.00
OH5 Raise, Surface and Line Track 4,200 TF $4.00 $16,800.00
OH6 Raise, Surface and Line Turnouts 2 ea $4,400.00 $8,800.00
OH7A Replace timber structure at MP 297.15 with CMP 1 LS $8,325.00 $8,325.00
OH7B Replace timber structure at MP 297.48 with CMP 1LS $9,972.00 $9,972.00
OH7C Replace timber structure at MP 301.30 with CMP 1 LS $9,910.00 $9,910.00
OH7D Replace timber structure at MP 301.60 with CMP 1 LS $11,600.00 $11,600.00
OH7E Replace timber structure at MP 302.00 with CMP 1 LS $10,420.00 $10,420.00
OH7F Replace timber structure at MP 303.40 with CMP 1 LS $9,770.00 $9,770.00
OH7G Replace timber structure at MP 304.20 with CMP 1 LS $11,269.00 $11,269.00
OH7H Replace timber structure at MP 304.50 with CMP 1 LS $9,486.00 $9,486.00
OH7I Replace timber structure at MP 304.80 with CMP 1 LS $13,154.00 $13,154.00
OH7J Replace timber structure at MP 306.90 with CMP 1 LS $11,140.00 $11,140.00
OH7K Replace timber structure at MP 310.90 with CMP 1 LS $9,198.00 $9,198.00
OH7L Replace timber structure at MP 312.35 with CMP 1 LS $11,059.00 $11,059.00
OH7M Replace timber structure at MP 313.90 with CMP 1 LS $9,889.00 $9,889.00
OH8 Furnish and install bridge ties at MP 313.20 1 LS $22,910.00 $22,910.00
OH9A Repair timber structure and install ties at MP 288.70 1 LS $24,789.00 $24,789.00
OH9B Repair timber structure at MP 300.62 1 LS $22,808.00 $22,808.00
OH9C Repair timber structure at MP 304.60 1 LS $47,332.00 $47,332.00
OH10A Concrete bridge repair and pointing at MP 309.10 1 LS $4,608.00 $4,608.00
OH10B Concrete and steel bearing repair at MP 311.85 1 LS $4,902.00 $4,902.00
OH10C Concrete repair at MP 300.38 1 LS $4,609.00 $4,609.00

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

June 17, 2013 - Notice to proceed issued.

August 20, 2013 - Material delivery begins.

August 26, 2013 - Change order 001. The following work is added to contract.

No.Item

Quantity

Unit Price

Extended Price
CO#1 OH2 Furnish and Install Track 1500 TF $94.00 $141,000.00
CO#1 OH3 Furnish and Install #8 Turnout 3 EA $59,950.00 $179,850.00
CO#1 OH4 Furnish and Install Stone Ballast 750 TN $34.00 $25,500.00
CO#1 OH5 Raise, Surface, and Line Track 1500 TF $4.00 $6,000.00
CO#1 OH6 Raise, Surface and Line Turnouts 3 EA $4,400.00 $13,200.00
Change Order 001 Total $365,550.00
Revised Contract Total $1,282,450.00

 

 

 

 

 

 

 

August 29, 2013 - RWS Training and start of work.

September 30, 2013 - Change orrder 002. The following modification to exising work is made.

No.Item

Quantity

Unit Price

Extended Price
CO #002 Change from standard to insulated for turnout at MP 298.7 1 LS $5,687.00 $5,687.00
Change Order 002 Total $5,687.00
Revised Contract Total $1,288,137.00

 

 

 

 

 October 31, 2013 - Work suspended for winter.

April 3, 2014 - Work resumed.

April 17, 2014 - Work complete.

April 23, 2014 - Final inspection by railroad.

May 28, 2014 - Work accepted by NY DOT.